SEWER MANIFOLD REPAIR 4
Sewer manifold rehabilitation works were executed.
• Loose concrete layers were removed
• reinforcing
• 50mm В30W100F300 shotcrete layer was applied
• all surfaces injected with epoxy
• A waterproof coating based on two component mastic was applied
Work execution period stood at 12 working days.