        Structural shotcrete implies manufacturing of products and structures directly at a construction site by shotcreting (maximum filler size up to 12 mm) on a stable surface (one-sided timbering, soil, prepared concrete or masonry construction) with subsequent finishing. Concrete application and compaction is accounted for pneumatic power. Obtained concrete possesses a closed pore structure and, as a result, increased waterproofing, frost resistance and longevity. Shotcrete is a good alternative to vibrated concrete when fabricating structure walls, constructions in hard-to-reach spots, curved surfaces, thin-walled shells, relieving and pressure walls with surface decoration.

     There are examples of executed works in the section IMPLEMENTED PROJECTS and on the websites of foreign companies: www.shotcreteinc.com, www.therixgroup.com.au, www.fishershotcrete.com, www.torrentshotcrete.com

   Structure fabrication advantages using shotcreting:

  • timbering construction savings up to 100 %;
  • irregularly shaped structure fabrication;
  • significant reduction or total rejection of load lifting equipment;
  • visual control of concrete placing and compaction, particularly when fabricating reinforced concrete structures;
  • time, material and labour resources savings up to 70%, thus ensuring high economical efficiency.

Area of application examples: 

Examples of works

BUILDING BLOCK MODULE

Building block modules were manufactured along external timbering using fibrous B40 shotcrete. Wall thickness stood at 25-30 mm. Floor and ceiling thickness stood at 30-35 mm

CHURCH DOME CONSTRUCTION

Thin-walled shells (80 mm thick), the central church dome (11 m in diameter), 4 lesser domes (6 m in diameter) and the vault under the central church dome (10 m in diameter) - all these were manufactured using shotcrete.

SEWER MANIFOLD REPAIR 2

Reinforced concrete encasement was manufactured inside an existing 100 meter long sewer manifold under a functional railway. Waterpoofing and double reinforcement were performed. 200 mm of concrete were applied using В30W8F300 shotcrete.

TUNNEL WALL CONSTRUCTION 2

Levelling wall area stood at 2,500 m2 and pressure wall area stood at 2,000 m2. Levelling and pressure walls and pump house walls were constructed along bored piles using В30 W8 F300 shotcrete to a thickness of 100-500mm. 2,300m3 of concrete were placed over 3 months.

POND CONSTRUCTION

Pond (irregular shaped) construction works were executed. 35 m3 of В30F300W8 concrete (betonat) were placed. Work execution period stood at 2 days.